Arapahoe County outlines proposed 90-day review for affordable housing
Applicants could opt into the process for qualifying projects with at least half their housing units affordable, subject to review deadlines and specified extensions.

Published at
Arapahoe County has outlined an optional fast-track process that would aim to deliver a final decision on qualifying affordable-housing applications within 90 calendar days after an application is complete. The process could end in approval, approval with conditions or denial; it would not guarantee approval, the County’s proposed outline says.
Colorado requires local governments to demonstrate by Dec. 31, 2026, that they have implemented a fast-track review process to remain eligible for future Proposition 123 funding and commitment cycles. The process must take effect Jan. 1, 2027, the Colorado Department of Local Affairs says. County staff said failing to adopt the process by the end of 2026 could put the County’s and certain qualifying projects’ access to funding opportunities during the 2027–2029 commitment period at risk.
In a report prepared for the Board’s Nov. 10, 2026, agenda, staff asked commissioners, if they found the proposal acceptable, to place a resolution adopting the process on a future meeting agenda, the staff report says. The request is a proposed next step, not adoption of the process.
To qualify, a project would need to meet the state-law definition of affordable housing, with at least half of its housing units meeting that definition. For mixed-use developments, the threshold would apply to the housing units, not the entire project. Eligible application types would depend on zoning and could include site plans, some use reviews, engineering plans and building permits. The outline excludes subdivisions, rezoning, new planned unit developments, location-and-extents applications and projects without housing.
Applicants could choose the fast-track pathway and withdraw by notifying the County in writing. The process would begin with a presubmittal meeting, scheduled within five business days, involving County Planning, Engineering and Building staff and the Southeast Metro Stormwater Authority. The 90-day clock would start after that meeting once staff finds the application complete.
The outline sets a 10-business-day period for the first department review and five business days for later reviews. Applicants would have 10 business days after the first review meeting to resubmit, then five business days after later meetings. Eligible building permits could be submitted alongside site plans and receive priority review. Live reviews would be available for third and later planning and engineering reviews.
The County could grant one 90-calendar-day extension at an applicant’s request. The outline also allows extensions for time required by state law or court order, reviews by another government or agency, and time an applicant needs to respond to County requests for information or revisions. For applicant responses, the extension would be capped at the response period plus 30 days.