Littleton commission approves conceptual plan for Bible college at former headquarters
The approval allows the institute’s proposed reuse under business-center zoning, but an adaptive-reuse permit and further code reviews are still required before construction.
Published at
Littleton’s Planning Commission voted 6-0 on Nov. 9 to approve a conceptual plan for Bear Valley Bible Institute to reuse its former headquarters at 7926 S. Platte Canyon Road as a college and ministry training center. The commission’s vote approves a development framework, not permission to begin construction.
The plan removes the property’s planned-development overlay, allowing the underlying Business Center zoning to apply. That zoning permits private colleges and universities, as well as offices, the city’s resolution and staff report explain. The institute proposes to use the existing building for about 60 students and roughly 70 daily users, with no building or site expansion and no additional parking.
Before construction, the institute must obtain an administratively reviewed adaptive-reuse permit. Stormwater reviewers said existing facilities are adequate for reuse if site conditions remain unchanged apart from maintenance; further stormwater details and applicable building and utility requirements will be reviewed later.
A traffic consultant projected 414 weekday trips for the proposed use, compared with 402 for the former office use: 12 more total trips, four more in the morning peak hour and eight fewer in the afternoon peak hour. The estimate used a 120-student scenario—twice the proposed enrollment—and an office-building model for both uses. It is a projection, not a traffic count.
The existing parking lot would remain, but the shared parking arrangement with the Edge Volleyball Club will end under the institute’s ownership, the city’s packet says.