Littleton council to consider $175,428 more for Elati storm-sewer repairs
A proposed contract amendment would bring the emergency repair total to $651,885.96 after crews found a 283-foot collapsed pipe section and eight other damaged or at-risk sections.

Published at
Littleton City Council is scheduled to consider a $175,427.96 increase to the emergency contract for Elati Street storm-sewer repairs, bringing the total to $651,885.96 and extending the completion deadline to April 30, 2027. The Nov. 17 council packet places the proposed amendment on the consent agenda.
The city’s staff report lists the existing contract at $476,458. The increase would cover expanded work after crews found the collapsed pipe section was 283 feet long, rather than the roughly 20 feet initially expected. The proposed amendment calls for full excavation and replacement of that section, along with work on eight other damaged or at-risk sections, pipe bedding and restoration.
The pipe failure south of South Sundown Circle created a sinkhole in the sidewalk and adjacent bike lane, the staff report says. The city said it completed repairs needed to reopen the road and sidewalk before school began in August. It had scheduled work at the Elati Street and Ridge Road intersection during the schools’ Oct. 15-19 fall break. The intersection is near Heritage High School and Runyan Elementary School.