Denver Water staff propose delaying raw-water drought rates until May 2027
The change would keep raw-water customers on base rates for four additional months while other customers’ drought rates begin Jan. 1. Staff estimate it would reduce 2027 revenue by about $390,000 if drought conditions persist all year.

Published at
Denver Water staff recommend delaying drought-rate charges for raw-water customers until May 1, 2027, while other customers’ drought rates would begin Jan. 1. The Board of Water Commissioners is scheduled to consider the change Nov. 18 as an amendment to the 2027 drought-rate schedule, staff recommend.
If approved, raw-water customers would continue paying previously approved base rates from Jan. 1 through April 30. Staff say the delay responds to customers’ concerns about the timing and gives them more time to establish ways to recover costs. They say raw-water uses, delivery methods and conservation capabilities differ from those of treated-water customers, and describe the change as a one-time accommodation.
The timing change is separate from the broader 2027 rate package, which the Board approved unanimously Oct. 28. Rates and drought rates in that package were generally set to take effect Jan. 1; the raw-water timing amendment is scheduled for a separate decision.
Staff estimate the delay would reduce 2027 revenue by about $390,000 if drought conditions continue throughout the year. The reduction would be smaller if drought conditions end sooner.