Denver committee approves $10.3 million airport train contract increase

The amendment adds signaling and communications equipment to 19 new cars during manufacturing, aiming to avoid retrofits and support testing of a separate system upgrade.

Train inside Denver International Airport’s underground transit system.
Train inside Denver International Airport’s underground transit system.
"Denver airport train", by beratus, CC BY-NC-SA 2.0

Published at

Denver’s Transportation and Infrastructure Committee approved a $10,296,300 increase to Alstom’s contract for Denver International Airport’s automated guideway transit system, bringing the contract total to $80,237,300. The amendment covers signaling and communications equipment, wiring and installation in 19 new 300R cars, the committee approved at its Nov. 18 meeting.

The committee’s approval was not final City Council approval. The amendment was listed for consideration at Denver’s Nov. 24 Mayor-Council meeting, but the meeting was canceled, so the council did not vote on it at that meeting, the agenda says.

Denver says installing the equipment during manufacturing is intended to avoid later retrofits, preserve compatibility with the airport’s existing signaling system and provide cars for testing a separate system upgrade, as described in its contract request. The request says retrofits could delay testing and broader system revitalization because an expansion of the maintenance facility is expected to constrain workspace and access. Installing the equipment during manufacturing is also intended to minimize passenger impacts and support future demand associated with the C West Expansion, as well as system growth and operational reliability.