Denver committee backs airport train equipment amendment
The amendment would add signaling and communications equipment to 19 new cars during manufacturing, aiming to avoid retrofits and support testing for a planned system upgrade.

Published at
Denver’s Transportation and Infrastructure Committee approved an amendment to Alstom’s Denver International Airport train contract on Nov. 18 that would add signaling and communications equipment to 19 new cars during manufacturing, the committee’s action record shows.
The committee’s approval was not final City Council approval. The amendment was listed for consideration at the Nov. 24 Mayor-Council meeting, which was canceled. As of Nov. 25, Legistar’s matter history showed committee approval but no subsequent Council adoption.
The resolution lists a $10,296,300 increase and an $80,237,300 maximum contract liability. The attached variation-order proposal prices the added work at $9,978,121.69, a difference of $318,178.31; the amendment and its attachments do not state a separate increase.
The 19 new APM300R cars are planned to enter service using the existing Cityflo 550 configuration. The amendment also includes Urbalis Flo signaling equipment for controlled testing and future flexibility as Denver plans a transition to its Vision 100 system; it does not provide a complete operational system. Testing plans include single-car and coupled-car scenarios.
Denver says installing the equipment during manufacturing is intended to avoid later retrofits, preserve compatibility with the current signaling system and provide cars for testing the upgrade, as the city described in its contract request. The request says retrofits could delay testing and broader system revitalization because the maintenance-facility expansion is expected to constrain workspace and access. The approach is also intended to minimize passenger impacts and support future demand associated with the C West Expansion, system growth and operational reliability.
The attached delivery schedule is preliminary and assumes a Dec. 15, 2026, notice to proceed. It lists the first vehicle arrival for April 5, 2028, and the last for Feb. 26, 2029; the schedule says it will be finalized after the notice to proceed and coordination with the factory portfolio.