Wheat Ridge designs replacement for closed Oak-Twilight crossing, targets spring completion

The project is estimated at about $500,000, with city budget funding identified and a possible county contribution. The city hopes to finish before irrigation water returns in spring 2027.

Published at

Wheat Ridge is designing a replacement for the closed pedestrian crossing near Oak Street and Twilight Drive and hopes to finish before irrigation water returns in spring 2027, advancing a project that previously considered several options.

A city staff member told the City Council on Nov. 9 that the replacement was “in design right now” and that the city was rushing to build the path before the ditch reopened, which staff said would be before April 2027. Staff estimated the project at about $500,000 and said the city had identified budget funding. Jefferson County Open Space might contribute additional funding, but that contribution is not confirmed, staff told the council. The timing is a target, not a guaranteed completion date.

The project’s approach has advanced since an Oct. 26 status update. At that time, the city manager said public works had received three engineering quotes for options including replacing the bridge or piping the ditch and building a path over it. The ditch company favored the piped-ditch option. The manager said the city was willing to seek a license to build and maintain a crossing, but no final agreement or project approval was reported; the council received a status update and did not vote. The city manager also said the existing bridge was closed at the ditch company’s request as a safety precaution. The city manager’s Oct. 26 update described an uncertain schedule. Work in the ditch is not allowed while irrigation water is flowing, which is expected to return in April 2027.

The city had identified budget funding and was seeking a Jefferson County Open Space grant, which the city manager said could cover 25% of the estimate. Lakewood had provided a letter of support but no project funding was available, the manager said. The county contribution remains unconfirmed.

The crossing served as a neighborhood walking route. A resident told the council on Nov. 9 that the closure had forced him to walk with his children along Oak Street to 32nd Avenue, near trucks and congestion. CBS Colorado reported that residents also used the crossing to reach school, friends’ homes and neighborhood activities, and that some considered alternative routes less safe. The city has not described an interim crossing or specific detour.