Broomfield council to discuss safe-parking expansion options

Staff estimate one approach would cost about $190,000 a year; a 30-vehicle site could cost $630,200 annually, plus up to $2.44 million to prepare.

Aerial view of RVs and trailers parked in an organized lot.
Aerial view of RVs and trailers parked in an organized lot.

Published at

Broomfield City Council is scheduled to discuss two ways to expand safe parking for people living in vehicles on Nov. 17. The city’s current sites accommodate 13 passenger vehicles and three recreational vehicles, while the five-site regional network has a waitlist of 16 cars and 16 RVs, a city staff memo says.

One option would add staffing and support at existing faith-based lots, where participants park overnight and move their vehicles daily. Staff estimate it would cost about $190,304 a year, could roughly double overall vehicle capacity and add two RV spaces. The memo does not specify a guaranteed final capacity or vehicle mix.

The other option is a 24-hour Supportive Parking site with a baseline capacity of 30 vehicles — about 15 cars and 15 RVs or trailers. Participants could stay up to 12 months, with possible extensions for people actively seeking housing. Staff estimate annual operating costs of about $630,200, assuming an existing parking facility. Potential city-owned sites identified in the memo lack parking lots and infrastructure.

Preparing a new one-acre site could cost an estimated $550,296 to $2.44 million, depending on utility hookups. The lower-cost “dry lot” scenario includes one electric hookup and no water or sewer hookups; the highest-cost scenario includes full hookups at all 15 RV spaces. Other listed needs include fencing, drainage and lighting.

Neither option is funded in Broomfield’s 2026 or 2027 budgets. The Nov. 17 session is scheduled as a discussion, not a final decision. Staff are asking whether the council wants further exploration of either option in 2027. If the council favors studying Supportive Parking, staff also seek direction on the operating model and whether to study a new lot or an existing property.