Douglas County staff recommends $101 million plan for Zebulon sports complex

The Nov. 24 package also includes a land exchange and two project agreements; the $4.315 million design phase does not fund construction.

A site-plan rendering for the proposed Zebulon Regional Sports Complex shows its planned building, sports fields, parking areas and internal paths.
A site-plan rendering for the proposed Zebulon Regional Sports Complex shows its planned building, sports fields, parking areas and internal paths.

Published at

Douglas County staff recommends that commissioners approve a $101 million certificates of participation financing plan for the proposed Zebulon Regional Sports Complex, along with three related actions, at their Nov. 24 meeting. The recommendations are scheduled for consideration; commissioners have not yet taken action.

The plan would use voter-approved parks sales-tax revenue for early lease payments while the facility develops its own revenue. Staff projects that by the complex’s fifth operating year, September 2032 through August 2033, it would generate $7.60 million in net income available for lease payments. The staff report says the plan would not raise taxes and that facility income could eventually free parks-tax revenue for other county projects.

A draft financing resolution sets ceilings of $102 million in principal and $207 million in total lease payments over the term, with annual payments capped at $7.2 million and a maximum 5.60% net effective interest rate. Payments would be subject to annual county appropriation, and the lease could run through Dec. 31, 2056. These are proposed limits, not final borrowing or payment terms, under the resolution.

The other proposed actions would expand the project site and authorize additional design and infrastructure work. Under a land exchange, Sterling Ranch companies would transfer about 25.8 acres to the county in return for about 3.71 county acres, with no cash payment specified. The exchange amendment requires the property to be fully remediated before transfer and includes environmental-notice, pollution-insurance and other closing conditions. The county would also take on recorded environmental restrictions and related obligations tied to its ownership.

Staff recommends adding $2,255,437 to the infrastructure agreement, bringing the maximum reimbursement for verified costs to $14,301,733. The amendment attributes the revised scope and costs to grading changes, offsite utilities and waterline extensions along Waterton Road.

The final proposed action is a $4.315 million Phase 2 agreement with KT Development for detailed design and preconstruction work. The design-build agreement includes a 10% contingency and calls for developing a guaranteed maximum price for construction. Construction itself is not funded or priced by the agreement; it would require a later acceptable price, board approval, an appropriation and a notice to proceed. The planned complex would include ice sheets, multi-sport courts, fitness facilities and outdoor fields; an aquatics center is being developed separately.