Dominion seeks approval for Sterling Ranch sewer pump station

Douglas County’s Planning Commission is scheduled to consider the project Dec. 7; the station is planned to serve Sterling Ranch’s projected 2035 buildout.

Open field with low grass, shrubs and fence posts at the proposed lift station site.
Open field with low grass, shrubs and fence posts at the proposed lift station site.

Published at

Dominion Water & Sanitation District is seeking Douglas County approval to build a wastewater pump station and about 1,143 feet of pressurized sewer pipe in Sterling Ranch, where future development cannot rely on gravity sewer alone, the county’s staff report says. The Planning Commission is scheduled to consider the application Dec. 7, according to the county meeting notice.

The proposed Willow Creek Lift Station No. 2 would occupy about three-quarters of an acre at 9292 North Rampart Range Road. At Sterling Ranch’s projected 2035 buildout, its service area would include 1,744 single-family lots, commercial uses and a school. That projection describes the future service area, not the number of homes expected to connect immediately.

The district plans to build the station in two phases. The first, scheduled from summer 2027 through spring 2028, would include the wet well, pump building, site work and pipeline. The second, planned from summer 2028 through spring 2029, would add pumps, a generator and electrical and operating equipment. The district expects the station to be operational in spring 2029. The staff report estimates construction traffic at 10 to 20 trips per weekday and routine operations at two to four vehicle trips a day.

The pump building site is outside the mapped 100-year floodplain, but the pipeline would cross it and a small intermittent stream. The applicant’s environmental consultant considers the stream state water and expects the crossing could qualify for a Colorado general authorization, subject to state review and applicable conditions.

County approval alone would not authorize construction. The district would still need final construction plans, drainage and erosion-control reviews, access and building permits, state wastewater approvals and utility easements.